1, composition of the cement silo
50TON,80TON,100 tons,120TONS,150TON of bulk cement silo consists of the following sections: warehouse steel structure parts, ladder, guardrail, tube, precipitators, pressure relief valve, high and low level meter, discharge valve.
2, the cement silo structure

2013 Cment silos for sale

2013 Cment silos for sale

100 tons of bulk cement silo is a cylindrical structure supported by four tube legs at the bottom of the entire positions in the body, the whole warehouse all in the form of steel structure welded; top of a filter and pressure relief valve.
3,Cement silo works
1. when 100 tons of bulk cement silo work must be performed by a dedicated crane to erect, and then into the pre-prefabricated concrete foundation, and check the 100 tons of bulk cement silo erected after the vertical and the horizontal degree, and then firmly welded to the bottom base of embedded parts.
2.The secured storage silos, bulk cement truck transportation of cement to the site, then the bulk cement truck transmission pipeline with 100 tons of bulk cement silo feed piped through the gas pressure of the bulk cement truck tank within the cement is delivered to the 100 tons of bulk cement silo.
3.To transport cement storage silos, press the button of the precipitator vibration motor operator uninterrupted, and shake off the cement attached to the dust collector bag to prevent blocked bag warehouse explosion occurs.
4.Once blocked bag, positions within the pressure exceeds the pressure relief valve of the warehouse roof safety pressure release compartment pressure, the pressure relief valve to open to prevent the occurrence of the warehouse explosion accident.
5. the level of material position can be observed to the positions full and Queliao.
6. when discharge is required, the first to open the cone bottom of the discharge valve manually, and then the cement fed out by cement conveying apparatus. In the discharge process, if there is a “bagging” phenomenon, timely pressing the arch breaker solenoid valve button, blowing, eliminating the “bagging” feed, to ensure smooth supply of cement.
7. when the conveying means of cement failure, the first manual unloading of the cone at the bottom of the valve, to prevent cement spillover wastage. 